Advantages
  • Dry construction technique
  • 50% faster than traditional masonry construction
  • Lead in time is generally 13 weeks from the order, or frozen design, whichever is the later to commencement of the ring beam
  • Buildings with floor areas up to 1000 sqm are on average constructed with a cycle time of 3 weeks for the first storey and 2 weeks per floor thereafter
  • Pre-engineered components ensure an accurate structure

Back To Metframe - Product List



  • Ability to incorporate concrete floors
  • Flexibility to incorporate most cladding systems
  • Offsite fabrication of wall panels
  • Erection rarely hampered by weather
  • Inert frame producing no settlement allows external masonry leaf to commence immediately behind window installation
  • Rapid dry envelope, allowing early commencement of dry lining and non-load bearing partitions, first fix MandE services